Painting Prep Update

As you've hopefully heard from us by now, a new EPA rule went into effect one year ago that states that it must be assumed that any home built prior to 1978 has lead in the paint--unless properly tested.  Testing for us here in California is somewhat cost prohibitive (although we did do a bit of testing on some of these homes); therefore we must assume any home built prior to 1978 does contain lead in the paint.  Because of this, we are required to follow the EPA RRP (Renovation, Repair & Painting) rule and adhere to certain protective practices when scraping or disturbing any paint on these homes so as not to create lead dust and to contain any paint particles we remove.  Unfortunately, the practices are so stringent that we are not able to do any scraping on Rebuilding Day.  (However, if there is less than 20 square feet of peeling paint on the exterior, the rule does not apply.)

So, we have identified those projects doing exterior painting that need scraping, and we have scheduled prepping days throughout this month to scrape those homes.  Many thanks to the volunteers who've been Lead Certified and those who've been helping with this on a regular basis as well as Nicole Mueller, our AmeriCorps volunteer who has been dedicating most of her time coordinating these efforts!

Here's a rundown of the exterior paint conditions, and prepping that may or may not occur prior to Rebuilding Day.  If you have any questions, please let me or Nicole know (nmueller@rebuildingtogether-sv.org).

At this time we are not doing any interior prepping because the requirements for interior work is simply too difficult to manage if not done in conjunction with the painting.  It is our understanding that all interiors being painted do not require any scraping.  


Project # Homeowner Name Paint Prep update
120 Brazwell <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
121 Nguyen prep will occur on 4/20
122 Segura prep will occur on 4/9
123 Teso tested negative for lead, prep can occur on Rebuilding Day
124 PACE MoreHouse no exterior painting
125 PACE Miracle House no exterior painting
126 Purcell prepped 4/1
127 Martha's Kitchen no exterior painting
128 Rodriguez prep will be done by Vivid Painting
129 Moore prepped 4/4
130 Hobbs prep will be done by Vivid Painting
131 Almanza prep will occur on 4/25
132 Posada no exterior painting
133 Golden Care no prep required
134 Fisher <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
135 Bemont prep will be done by Vivid Painting
136 Wade House built after 1978, no pre-Rebuilding Day prep required
137 Argandar <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
138 Kotwicki prepped 4/6
139 Ahmad, Mahmoud no exterior painting
140 Ramirez no exterior painting
141 Caballero prep will occur on 4/8
142 Casa de Clara no exterior painting
143 Young Life Capernaum no exterior painting
144 Keith prepped 3/23
145 Moralez prep will be done by Vivid Painting
146 Cardenas no exterior painting
147 Evanoff prep will occur on 4/13
148 Velarde prep will occur on 4/18
149 Galvan prepped 3/28
150 Flores, R. prepped 3/30
151 Flores, F. no exterior painting
152 Avalos tested negative for lead, prep can occur on Rebuilding Day
153 Gaspar prep will be done by Vivid Painting
154 Hernandez <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
155 Hannibal prep will occur on 4/27
156 Holland tested negative for lead, prep can occur on Rebuilding Day
157 Valenzuela prepped 4/6
158 Red no exterior painting
159 Armas no exterior painting
160 Chavez no exterior painting
201 Garcia <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
202 Chen no exterior painting
203 Truchetta <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
204 Connelly no prep required
205 Perazzo no exterior painting
206 Carver no exterior painting
207 Aguirre pergola being removed prior to Rebuilding Day
208 Morales prep will be done by a City of San Jose contractor
209 Gibbons no exterior painting
210 Marumoto <20 sf peeling exterior, no pre-Rebuilding Day prep required, prep can occur on Rebuilding Day
211 Woods awaiting decision regarding exterior painting